Re: How to create or set cost to a work order ?

$
0
0

Hi,

 

This should be done by users in Finance department. However, this is easy. In T-code KP26 enter the following:

 

Version: 0

From: 3 (current period)

To: 3 (current Period)

FY: 2016

Cost Center: relevant cost center (this be available as error in IW33 log as error, in case you released the order without price)

Activity type: enter activity type ID like labour, machine, etc.

 

- Once you fill the data click on the Overview button. on the subsequent screen enter the price that will multiplied in the number of hours for the relevant activity.

 

Regards,

Ibrahim Mohamed