Re: How this mrp run takes place,sometime customer requirement getting substracted and some time not

Hi Ajit,

 

You might want to look into "transfer of requirement" when Sales interacts with Production. As already explained by Experts above, there are object / settings responsible transfer of requirement.

 

For example, go to a sales order, under procurement tab and check the requirement type assigned to material. This controls if it has to be MRP relevant or not, and transfers the requirement to production via requirement planning.

 

Regards,

Rohit